August
2009
Last step...the Main Street facade power-washed and repainted by Painting by Northeast
|
|
July
2009
Structural renovations on the Main Street complex are completed! |
|
June
2009
Lawn in front of Program Center re-seeded.
|
|
March
2009
Upper floors strengthened with new framing. Access and venitlation restored to attic spaces.
|
-------------------------------------------------------------------------------------------------------------------------------------------------------------->> |

February
2009
Three steel beams are craned into the buildings for support.
Also, real-time slideshow of the renovations goes online.
|
|
January
2009
Work is done in the basements to remove rubble, repair sills and framing, install concrete slabs, and dampproof.
 |

December
2008
Exterior sitework accomplished to install dry well to improve drainage systems. Also, carpenter shed demolished.
|
November
2008
Additional studies and plans made for submission for building permits and approvals from the Kennebunk Historic Preservation Commission. |
|
|
|
August
2008
Donors honored and thanked at Appreciation Event

|
|

June
2008
Commemorative bricks are installed in the courtyard walkways.
|
-------------------------------------------------------------------------------------------------------------------------------------------------------------->> |
April
2008
On the move! Museum staff and volunteers receive training and start packing the china, glass, and fine arts collections for the move.
|
|
January
2008
Plans are underway to temporarily move the contents of the Museum's archives building to offsite storage, in anticipation of repairing the structural issues in this edifice first. Inventorying continues throughout the winter.
|
September
2007
Repainting the exterior of the Brick Store building is completed
|

July
2007
Campaign tops the million-dollar mark!
|
|

Repointing and chimneys completed

Demolition continues on private property adjacent to the Museum and, as a result, opens up the approach to the Museum's entry walkway.
|
|
May
2007
Repair of front chimneys begins; banner goes up on scaffolding anticipating the repointing on the Main St. facade
|
|
April
2007
Repointing of the north wall completed

|
-------------------------------------------------------------------------------------------------------------------------------------------------------------->> |

March
2007
Rear chimney repaired. Work begins on repointing the north wall
|
|
February
2007
Completion of repointing of the Museum's south and east walls

|
|
December
2006
Scaffolding set and repairs to brickwork begin

|
|
|
|
October
2006
Campaign crests the halfway mark.
 |
|
Campaign banners installed.
|
-------------------------------------------------------------------------------------------------------------------------------------------------------------- * |
August
2006
Campaign website launched.

|
|
Connecting Generations 2006 Capital Campaign enters public phase with $650k in hand
|
June
2006
Campaign is publicly launched on June 20 at the 66th Annual Members' Meeting at The Colony Hotel. WCSH6 anchor Bill Green gives the keynote address.
|
Kennebunk Savings Bank Foundation makes lead gift pledge of $100,000.
|
|
|
|
June
2005
Campaign previewed at Museum's 2005 Annual Members' Meeting.
|
|
Comprehensive engineering study completed on Museum's buildings.
|
| |